Grant Road sinkhole informs East Wenatchee’s plan to replace aging Ninth Street pipe

Posted

EAST WENATCHEE – The call came about half an hour after Garren Melton’s predecessor walked out of the office. A sinkhole had opened on Grant Road.

The bottom of a decades-old stormwater pipe had corroded, allowing sand to wash out from beneath the road. When the pavement gave way, the city had to reroute commercial traffic, adjust Link Transit bus service and figure out how to keep deliveries moving to Fred Meyer. Replacing a short section of pipe cost about $330,000, Melton said.

Now East Wenatchee’s public works director, Melton brought that experience to the City Council on Nov. 17 as it approved an $88,309 agreement with RH2 Engineering to design the first phase of a stormwater pipe replacement on Ninth Street NE.

“This is the one that had kind of kept me up at night over the last few years,” Melton said.

Crews got a look at the Ninth Street pipe during traffic signal work in 2021. The 12-inch corrugated metal pipe was undersized and nearing the end of its useful life, according to a city staff report. The first phase will replace it with a larger pipe between Valley Mall Parkway and Colby Court, across from City Hall. A later phase would extend the replacement to Eastmont Avenue.

Construction is expected in summer 2027. The East Wenatchee Water District plans to replace service lines in the same area, and city crews plan to install conduit at Ninth Street and North Baker Avenue while traffic is already disrupted. The city has received $1.8 million for a future intersection improvement there. Melton said a traffic signal is more likely, though a small roundabout is also under consideration. The city plans to repave the full width of Ninth Street along the first phase.

The stormwater work is estimated to cost about $690,000 for design and construction. Melton said he discussed the project with the Finance Committee but missed entering it in the city’s budgeting software. Finance Director Josh DeLay added it to the proposed 2027 budget, which returns to the council for a vote Dec. 1.

The engineering agreement also includes camera inspections of about 5,300 feet of other corrugated metal stormwater pipe around the city. Those inspections will give East Wenatchee a closer look at which pipes may need replacing before the pavement above them gives way.